[00:01]
In 2022, the world got a very cool new bridge.
[00:08]
Bridges carries Interstate Highway 74 over the
[00:14]
Bettendorf, Iowa in the “Quad Cities” area. It’s a
[00:21]
arches carrying each deck over the main span of
[00:27]
DOT had a problem. The two old bridges were still
[00:34]
And even though they were kind of cool looking,
[00:39]
in poor condition, and without extensive ongoing
[00:45]
posing a danger to the public, affecting
[00:49]
and even disrupting this critical shipping
[00:55]
Demolition, on its face, seems kind of easy.
[01:00]
the demo part feels almost like housekeeping.
[01:06]
then just pick up the pieces. No engineering
[01:12]
Demolition engineering, in many ways, is even
[01:17]
and the I-74 bridge is the
[01:21]
And don’t worry, there are explosions at the end.
[01:34]
The original I-74 bridges, with just two lanes
[01:41]
This is actually a problem they faced and managed
[01:47]
Despite looking like twins, the original pair
[01:53]
first span was completed in the mid 1930s, but car
[01:59]
Engineers decided that the best way
[02:03]
nearly identical bridge right next to
[02:09]
Neither bridge was ever intended to meet
[02:13]
interstate system altogether. And yet, they found
[02:19]
way beyond what the designers in the 1950s,
[02:25]
had considered. The lanes were narrow, there were
[02:30]
which bottlenecked traffic on I-74.
[02:36]
were also just physically wearing out. Like an
[02:41]
cost of replacing the bridges was outweighed by
[02:48]
In 2012, Transportation Secretary
[02:52]
reporting back that it was, quote, “one of
[02:58]
You would think that already being close to
[03:03]
it comes to demolition, but it’s quite
[03:07]
were big bridges with 3 types of structural
[03:13]
truss units over the old non-navigable part
[03:18]
kind of act as connectors. And then you
[03:23]
I’m sure you want to see the explosion, and I
[03:28]
last step. Of course, there are lots of cases
[03:33]
down right away. You end up with a pile of rubble
[03:39]
equipment. It can be much quicker, easier, and
[03:45]
but it’s rarely true for bridges. Of course
[03:50]
Removing debris from below
[03:54]
Long reach excavators can sometimes handle
[03:59]
to rig the big stuff to be lifted out by
[04:04]
You also have shipping traffic to consider. This
[04:09]
inland waterway system, and closing it to clean
[04:15]
The other thing making it tricky, in this case,
[04:20]
living in the non-navigable channel below the
[04:26]
couldn’t use blasting or even temporary supports
[04:31]
to dismantle the bridges more carefully and
[04:37]
The strategy here was to sawcut all the concrete
[04:43]
equipment. An excavator with a slab crab
[04:48]
steel structure, swing around, and pass to a wheel
[04:54]
but it had to be done pretty carefully. Cutting
[04:58]
the reinforcement is cut too. And this is
[05:04]
using calculations and analysis not to design
[05:10]
like, “Can these concrete panels support
[05:16]
The answer was more complicated
[05:20]
engineers imposed pretty strict positional
[05:25]
in most cases making sure that the tracks of
[05:30]
stringers instead of relying on the concrete deck
[05:36]
Another challenge on the suspension span was
[05:42]
to dismantle the bridge, systematically working
[05:48]
if you take all the weight off one section of the
[05:54]
the trusses are going to bow, the towers are
[05:59]
the bridge prematurely. It’s just like re-racking
[06:04]
you take everything off one side of
[06:09]
So, on the suspension bridges alone, the
[06:15]
Some slabs were removed with
[06:17]
Others were popped up and left in place as
[06:23]
It’s a lot more work with a crane
[06:26]
way to get the deck off in a symmetrical way
[06:32]
Once the concrete deck was off, the contractor
[06:37]
and stringers that make up the bridge structures.
[06:42]
go cutting up a bridge willy nilly. This is
[06:48]
and that requires some structural engineering.
[06:53]
team wasn’t allowed to install temporary
[06:58]
So instead, they floated in the support on
[07:02]
the trusses into pieces small enough for the
[07:07]
The suspension spans were even more complicated.
[07:13]
piece of steel that’s under significant
[07:18]
it could cause sudden movements and
[07:23]
Those cuts have to be carefully sequenced. When
[07:28]
changes the stresses, shifting them around and
[07:34]
to check each step before you do it to make sure
[07:40]
or the environment. And there’s no way to know how
[07:46]
Instead, they had to create a structural computer
[07:51]
bridge in 3D. The order also matters.
[07:56]
One cool example of this:
[07:59]
the top chords of each truss weren’t installed
[08:05]
most of the load was being carried in the bottom
[08:11]
the whole truss responded by going into
[08:16]
The top chords were in tension and the bottom
[08:21]
what you would expect. That’s something that
[08:25]
having gone through the exercise of modeling the
[08:31]
modified, and retrofitted over the years. It was
[08:38]
The engineer even used old magazine articles to
[08:44]
Here’s another tricky part. To lift the
[08:49]
they had to put a crane on a barge. Anyone
[08:54]
not the most stable platforms for high-stakes,
[09:00]
add in huge loads and the need for precision.
[09:05]
these bridges, but that doesn’t mean it’s easy.
[09:11]
loads from lifting and swinging. Barges often
[09:16]
but there’s still a lot of engineering that goes
[09:21]
variety of loading conditions. Those calculations
[09:28]
limitations on pick weights and movements, et
[09:33]
And just like the concrete deck, these
[09:37]
staggered manner to keep the towers from
[09:42]
Interestingly, sometimes to demolish a structure,
[09:48]
load system had to be removed because of
[09:53]
but the engineers didn’t want people working on
[09:59]
So they had to design and build these steel
[10:04]
the superstructure during the demolition process.
[10:09]
restraints on the trusses of the continuous
[10:14]
time those trusses were partially demolished. And
[10:20]
stiffening truss, made from pieces of the bridge
[10:25]
truss could be lifted and removed as a single
[10:31]
on the shore where it could be cut down using this
[10:37]
At this point, basically all that was left of
[10:43]
Since those cables are essentially one long
[10:47]
safely cut them loose. Imagine getting snapped by
[10:54]
up energy there, and you don’t want any humans
[10:59]
explosives come in. And like every other part
[11:05]
Explosives used for demolition aren’t
[11:10]
You’re not trying to use them to
[11:15]
On buildings, you get a lot of breakup anyway
[11:20]
But really, the explosives are just strategically
[11:26]
falling process in a more controlled way.
[11:32]
pieces that can easily be removed from the
[11:37]
very exciting saws that can cut
[11:43]
Demolition contractors use shaped
[11:48]
in a relatively controlled manner, and
[11:53]
It matters a lot what these pieces look like
[11:57]
to be lifted and transported out of the water. And
[12:03]
they’re accessible without blocking the navigation
[12:09]
there’s an entire process of precutting. The goal
[12:15]
be placed down to flat plates or smaller sections
[12:22]
A worst case scenario is an incomplete
[12:27]
bring the structure down. When that happens,
[12:33]
and difficult because you have to finish
[12:38]
it’s not entirely clear where the
[12:43]
On the I-74 bridges, workers cut the outer
[12:49]
the 37 strands holding. This was done in four
[12:55]
manageable pieces. The towers were also cut in
[13:01]
to sever completely and control which direction
[13:07]
this leaves the bridge extremely vulnerable.
[13:12]
stability so that the explosives can kind of carry
[13:18]
down. But it means the clock is ticking. You’re
[13:23]
don’t want a storm bringing the bridge down before
[13:34]
I’ve mentioned a lot of pros and cons of explosive
[13:39]
than anything else: the spectacle.
[13:42]
You just can’t get around how
[13:46]
They got perfect shots for both bridges, bringing
[13:52]
quickly to pick up the pieces. The road and
[13:58]
a short period of time. Here’s a good look at how
[14:03]
cables. And actually, they used explosives to demo
[14:09]
The piers in the more sensitive areas were taken out using conventional jackhammers as the final step. These sheet
[14:15]
pile containment structures kept the debris from
[14:20]
a scan to make sure all the debris was picked up.
[14:26]
habitat for those endangered mussels, so you can
[14:32]
But other than that, there’s almost no sign
[14:36]
I don’t just love bridges; I’m actually a
[14:41]
every year I have to take a certain number
[14:45]
And that’s how I first heard of this job.
[14:49]
put the story together in a
[14:52]
So huge thanks to them for sharing so
[14:57]
And another thanks to Iowa DOT who answered
[15:03]
I am so impressed with this bridge demolition. No
[15:09]
think taking the old ones down was the coolest
[15:15]
demolition is specialized, challenging work
[15:21]
Hats off to the entire team on this project
[15:27]
You know, I was super interested in that
[15:29]
sonar scan they did of the Mississippi River to
[15:34]
And really, I love any situation where you get
[15:39]
otherwise be hidden from view. My friend Brian
[15:45]
to a new level with his series, “The Anatomy
[15:51]
into a CT scanner, so we can literally see
[15:57]
of what makes up our favorite gadgets, like
[16:03]
RF shielding in the Nokia 3310. And if you want
[16:09]
You probably know about Nebula now, even if
[16:14]
built by and for independent creators. No studio
[16:20]
advertisements driving the content into a single
[16:26]
they’re excited about with as few barriers and
[16:31]
My videos go live on Nebula before they come out
[16:36]
I followed a large construction project from start
[16:42]
produced for Nebula viewers who want to see deeper
[16:48]
of streaming platforms out there right now, and no
[16:53]
but I also know that if you’re watching a show
[16:58]
on Nebula that you’re going to enjoy as well. So
[17:03]
you’ll get 50% off an annual plan. Pay just one
[17:10]
go.nebula.tv/practical-engineering. Or if you have
[17:17]
what I’m doing, you can get a lifetime membership.
[17:23]
Nebula last. If you’re with me that independent
[17:28]
I hope you’ll consider subscribing. Thank you